Major improvement work on A41 from Monday July 24
A north Telford and Wrekin road, is due for closure this summer and drivers are advised to follow diversions to avoid delays during the summer.
Major improvement works will take place on the A41 from Forton roundabout to Telford and Wrekin’s northern Shropshire boundary. Work will commence in line with school summer holidays while traffic volume is usually lower from Monday, July 24 and is expected to last until September.
The work will be supported by the council’s highways contractor Balfour Beatty and Idverde.
Councillor Lee Carter (Lab), Telford & Wrekin Council's cabinet member for place (the economy & neighbourhood services) said: “We’re pleased to be responding to requests from residents for improvement work and appreciate everyone’s patience and hope residents and commuters recognise that the ongoing investment into our network means we have some of the most satisfied drivers in the west midlands and continue to lead the way with highway standards.
“Work like this is always unpopular and it will cause some disruption but projects such as this are not undertaken lightly.
“This road first opened in 1985 – almost forty years ago – it’s been carefully monitored but the time for maintenance is needed now and will be carried out quickly and efficiently over the summer period with further improvement works planned for summer 2024.”
The work will include carriageway resurfacing and patching, ironwork reinstatement, drainage improvements, road sweeping, gully cleansing, tree felling, litter picking and improvements to road signs and lines.
Businesses along the route will be open as usual and access will be maintained by on-site Traffic Management operatives. Access will be maintained for residents.
The project scope includes more than a 1km of resurfacing, 150m of new drainage will be installed and more than 150 drains cleaned, 30 road signs replaced as well as work on the verges and road sweeping and is estimated to cost in the region of £900,000.
Updates around progress will be shared on the council's Facebook page or in the council's weekly email update which you can register for here.
The work is due to complete in September but is weather dependant which means programme dates are subject to change. For further details of the work including diversion routes, visit the website at www.telford.gov.uk/A41