Limekiln work to be completed later in the year

Work on Limekiln Bank Roundabout has been delayed by the utility companies meaning the roundabout cannot be finished until later in the year.

Limekiln work to be completed later in the year

The council has completed a lot of the work required, however some of the utility companies have failed to divert some of their apparatus on time and this is now holding up our work to finish the roundabout.

Unfortunately the council has no control over these utility companies and most of the outstanding diversion work can only be carried out by them. For us to continue with our work would ultimately mean any work we now carry out would be destroyed or damaged by the utility diversion work yet to be completed.

The council will provide a further update regarding timescales when we have agreed these with both our contractor and the utility companies concerned.

In the meantime, the council will ensure that traffic management is rationalised and the roundabout is allowed to operate as freely as possible while we wait for this work to be completed. 